INSTITUTIONAL DEVELOPMENT PLAN (IDP)

 

 (Under the World Bank supported Madhya PradeshHigher Education Quality Improvement Project)

2018-2023

To be submitted to

Department of Higher Education, Government of Madhya Pradesh

Year-wise Activity Plan

Year 1 - Detailed description of Milestones (Sub-goals)

Milestone (Sub-goal) 1

INFRASTRUCTURE

Example:

Increase in access by increasing intake from 1250 to 1500 by 2023.

S.N. Description Estimated cost(in Crores) Start Date End Date
  Smart Classroom      
  So far the college has only 2 smart classrooms and therefore only 100 students are able to avail the benefit of smart classrooms. 4.72    
1.         The 02 existing Smart class rooms need to be upgraded as only 100 students are accommodated in the present scenario. 01/04/2018 31/03/2019
2.         To Increase the number of classes further in smart class rooms, 02 new classrooms are to be constructed so that total 200 students can be accommodated. 01/04/2018 31/03/2019
3.         Maintenance of the 04 smart classrooms. 01/04/2019 31/03/2023
  PARKING
  The college has only 01 parking shed so far, catering to only 05 four wheelers We need to cater for parking for 60 four wheelers and 40 two wheelers.
1.         Parking sheds for 20 vehicles to be constructed. 01/04/2018 31/03/2019
2.         Parking sheds for 40 two wheelers will constructed. 01/04/2018 31/03/2019
3.         Parking sheds for 20 vehicles to be constructed. 01/04/2018 31/03/2019
4.         Parking sheds for 15 vehicles to be constructed. 01/04/2019 31/03/2020
5.         Maintenance of the parking sheds. 01/04/2020 31/03/2023
  CCTV Camera
  In order to enhance the quality of teaching and learning, strict monitoring of the classes and the campus is essential.
1.         CCTV Camera to be installed 01/04/2018 31/03/2019
2.         85 Cameras to be installed, once the budget is released. 01/04/2018 31/03/2019
3.         Maintenance of the CCTV Cameras. 01/04/2019 31/03/2023
  FURNITURE
1.         So far the institution has only 50% of the required furniture and almiras. 01/04/2017 31/03/2018
2.         25% of the furniture and almiras as required. 01/04/2018 31/03/2019
3.         25% of the furniture and almiras as required. 01/04/2019 31/03/2020
4.         Maintenance of 100% of the furniture and almirahas. 01/04/2020 31/03/2023
  Drinking Water Facility /Washrooms
  There is already a facility of drinking water. 3 Water coolers with aqua guard are already installed in the campus. The washrooms needs up-gradation and maintenance.
1.         Annual maintenance of aqua guard of all the water coolers. Up-gradation of washrooms. 01/04/2018 31/03/2019
2.         03 more water coolers to be installed and 03 washrooms to be up-graded. 01/04/2018 31/03/2019
3.         03 more water coolers to be installed. 01/04/2019 31/03/2020
4.         Maintenance of drinking water facility and washrooms. 01/04/2020 31/03/2023
  Campus Up-gradation
  There are many rare plants and medicinal plants available in the campus. Efforts will be made to protect them. Eco Parks will be developed in open spaces in the campus.
1.         The open space opposite A-Block will be developed. 01/04/2018 31/03/2019
2.         The open space opposite B-Block will be developed. 01/04/2018 31/03/2019
3.         The open space opposite AV-Block will be developed. 01/04/2019 31/03/2020
4.         Maintenance of all the plants and blocks. 01/04/2020 31/03/2023
  Electrification
  As the institution runs in a heritage building it requires constant monitoring of electric wiring.
1.         Planning and proposal for electrification to be sent, survey to be conducted. 01/04/2018 31/03/2019
2.         New electrification of A & B block. 01/04/2018 31/03/2019
3.         New electrification of P, G & H block. 01/04/2019 31/03/2020
4.         Maintenance of electrification of all the blocks 01/04/2020 31/03/2023
1.        Annual maintenance of aqua guard of all the water coolers. Up-gradation of washrooms. 01/04/201831/03/2019
2.        03 more water coolers to be installed and 03 washrooms to be up-graded. 01/04/201831/03/2019
3.        03 more water coolers to be installed. 01/04/201931/03/2020
4.        Maintenance of drinking water facility and washrooms. 01/04/202031/03/2023
 Campus Up-gradation    
 There are many rare plants and medicinal plants available in the campus. Efforts will be made to protect them. Eco Parks will be developed in open spaces in the campus.   
1.        The open space opposite A-Block will be developed. 01/04/201831/03/2019
2.        The open space opposite B-Block will be developed. 01/04/201831/03/2019
3.        The open space opposite AV-Block will be developed. 01/04/201931/03/2020
4.        Maintenance of all the plants and blocks. 01/04/202031/03/2023
 Electrification    
 As the institution runs in a heritage building it requires constant monitoring of electric wiring.   
1.        Planning and proposal for electrification to be sent, survey to be conducted. 01/04/201831/03/2019
2.        New electrification of A & B block. 01/04/201831/03/2019
3.        New electrification of P, G & H block. 01/04/201931/03/2020
4.        Maintenance of electrification of all the blocks 01/04/202031/03/2023
Resources required for theabove activities Resources available for the above activities    Resource Gap
4.72              100%

Persons responsible for conducting each activity

  1. Sudhir Kumar Sharma- Astt. Prof. – Sociology

  2. Shri S.S. Yadav – Astt. Prof. – Sociology

Persons responsible for monitoring each activity& its timely completion

Dr.Sudhir Kumar Trivedi- Prof. of History